231st St/G28 Paving Updates

Posted on: March 27, 2020

231st St/G28 Paving Update 3/27/20

March 27th, 2020

RE: CONSTRUCTION WORK ON 231ST  STREET (G28)

Dear Landowner or Resident,

As you may be aware, Muscatine County is planning to pave 231st St. (G28) from Independence Ave (X43) east to near Lutheran Homes.   We are planning to replace the existing road surface with a portland cement concrete pavement.  Portions of the pavement will be overlay (placed directly on the existing pavement), while other areas will consist of full grading of the roadway.  The project has been let to Peterson Contractors Inc. (PCI) of Reinbeck, Iowa, who will be completing most of the grading work.  PCI’s subcontractor, Heuer Construction of Muscatine, Iowa, will be paving the entire project.  The roadway will be closed to thru traffic for the duration of the project.  The direction of access will vary as construction progresses.  We recently held a preconstruction meeting for these projects and a timeline for starting the project is provided below.  Please remember that the dates may change due to the weather and the contractor’s work schedule. 


Beginning April 6th - Entire project will be closed to thru traffic.

Week of April 6th - PCI is planning to start prepping the overlay portions for paving

Week of April 20th - Heuer Construction plans to begin paving at Independence Ave and work their way east


Our office will continue to provide project updates, as construction progresses, and as more details become available.  Mailed updates will be rare due to the large number of residents along the project.  Residents are encouraged to visit the website below for more frequent project updates.

http://www.co.muscatine.ia.us/421/Construction


We understand that this is an inconvenience and we hope that it is minor compared to the improvements we will be making to 231st St.